Where is Rainier project headed?

5 years after voters approved an advisory measure calling for city to pursue its construction, proposed freeway interchange is still several years away

Terry Hankins
Yellow stripe shows where the proposed Rainier Avenue crosstown connector would extend under Highway 101 and west toward Petaluma Boulevard. The configuration of the planned interchange has not been decided.
Published: Friday, November 6, 2009 at 11:07 a.m.
Last Modified: Friday, November 6, 2009 at 11:07 a.m.

The Rainier cross-town connector and interchange has a funding plan, a traffic study showing it will relieve future congestion and $10 million allocated to it in the city’s redevelopment budget.

RAINIER’S TRAFFIC EFFECT
The addition of a Rainier cross-town connector and interchange would ease traffic congestion at other east-west routes in town, according to a city study.
Depending on which design option is selected, peak-hour afternoon traffic at the East Washington interchange would increase between 1.8 percent and 16 percent by the year 2040 with the addition of Rainier, a 2008 forecast report said.
If Rainier isn’t built, afternoon traffic there would grow by 43 percent by that year, the report said.
Either a traditional diamond interchange or a diamond with a northbound loop on-ramp at Rainier would provide the greatest traffic relief at other interchanges, the report showed.
By 2040, morning traffic volumes at East Washington would decrease slightly with a Rainier diamond. Afternoon traffic would increase by about 2 percent.

Without a Rainier diamond in place in 2040, morning traffic at East Washington would increase 42 percent and afternoon traffic 43 percent.
At the Old Redwood Highway interchange in 2040, morning volumes would grow by 26 percent and afternoon volumes by 28 percent under the diamond plan.
But without Rainier, morning traffic at Old Redwood Highway would increase by 52 percent, and afternoon traffic by 61 percent, in the year 2040, the report found.
The forecast assumes that planned improvements to each of those intersections would be complete and the freeway would be widened to three lanes each way by 2040.
The report was prepared by the city’s consulting firm, Carter Burgess, as part of an expected Caltrans study of the Rainier project.

Five years ago, it received the backing of 72 percent of Petaluma voters, who passed an advisory measure calling for the city to “pursue the design, environmental analysis, funding and construction” of the project.

What is doesn’t yet have, however, is final approval from state transportation officials.

Backers of the long-planned and sometimes-contentious project hope a key report on the feasibility of a new freeway interchange at Rainier Avenue will move the proposal closer to reality.

But when that report, first ordered in 2007, will be unveiled to the public is not yet known. It is being prepared by a transportation consultant, at the city’s cost, and must be approved by Caltrans.

Called a Project Study Report, the document is a detailed look at the cost, schedule and scope of proposed freeway projects, and is generally required as part of Caltrans’ approval process.

When the council voted to spend $449,000 in June 2007 to conduct the report, its findings were expected in about a year’s time.

In late 2007, the council voted to support what’s called a “design exception” allowing the new interchange to be built less than one mile north of the existing East Washington interchange, with the Project Study Report still due to be out in mid-2008.

That schedule slipped to August 2008, it was later reported, and officials later revised the timeline to the beginning of 2009.

The public works department, which is overseeing the planning for Rainier, noted in its most recent monthly update that the report had been submitted for Caltrans review in June of 2008, and that Caltrans had made its comments on the report in September of last year.

City Councilmember Mike Harris said he keeps hearing that the report’s release is close.

“In general, the pace is frustrating, but we have made some strides over time,” Harris said. “We are moving the ball forward.”

In October of last year, the council adopted a funding plan for Rainier that relies on traffic impact fees from new development, dedication of land from adjacent properties and the $10 million redevelopment contribution to pay for the project.

The exact cost will range between $38 million and $109 million, depending on which design alternative is selected.

In late 2008, a letter from Caltrans surfaced that seemed to cast doubt on the city’s preferred plan for Rainier — a diamond-style interchange estimated at $75 million.

The letter said that design may have “adverse effects” on the freeway, and suggested either not pursuing the project, building an undercrossing-only project or a more expensive system of frontage roads and ramps that connected the Rainier interchange with the one at East Washington.

City officials believe the use of auxiliary lanes — which would run between ramps on the south side of the Rainier interchange to ramps on the north side of Washington (including a new northbound onramp behind the Petaluma Plaza shopping center, now in the works) — would alleviate Caltrans’ concerns.

Such lanes, essentially an extra lane of the freeway in each direction along the stretch, would give merging drivers more space to mix with traffic in freeway lanes, and could be a way to address concerns about the less-than-one-mile spacing between the two interchanges, the city believes.

This week, Vince Marengo, the city’s public works director, met with Caltrans officials in Oakland but made no announcements about the project.

The department did state, however, that its design firm, Carter Burgess, has hired a transportation planning and consulting company “to assist the city in the coordination with Caltrans.”

The Walnut Creek firm of Grey, Bowen and Co. “will provide assistance to facilitate consensus between the city and Caltrans on the scope, limits and basic design features of the project,” the public works department stated in its monthly update.

The firm will also facilitate “Caltrans’ selection of the project alternative, approval of non-standard design features and approval of a new connection by the California Transportation Commission,” the department report said.

On its Web site, Grey Bowen said its “particular expertise” is the ability to combine transportation consulting with strategic project planning.

“We are able to understand complex policy approval processes while addressing difficult transportation and infrastructure problems,” the company states.

(Contact Corey Young at corey.young@arguscourier.com)


Comments

Only moderator-approved comments are shown on this page. To see all comments, please visit the forum.
    Post a comment | View all comments on this topic.
  1. SaveOurCity says...
    November 6, 2009 5:09:29 pm

    RE: Link

    "Build it and they will come!"

    Report this post

  2. Lidsville says...
    November 7, 2009 5:36:26 am

    par for the course here in slonoma county. someday people will wake up and vote out all these tree hugging anti-progressives....

    Report this post

  3. alive says...
    November 7, 2009 11:39:55 am

    I love how you Build-now-no-matter-what folks consistantly discredit yourselves by constantly pointing fingers at the same people no matter whose fault it is, instead of getting educated or even read the articles you are commenting on.

    Report this post

  4. Lidsville says...
    November 9, 2009 7:36:03 am

    In any community not located in the 'Liberal, tree hugging' bay area we'd be using this offramp TODAY.... Most, if not ALL, of the problems in the bay area can be attributed to rampant extreme left wing liberal policies. It's the reason we have to travel to RP or SR to shop, have schools where English is treated a second language, roads with potholes, lack of affordable housing, rampant illegal immigration, gangs, graffiti, high unemployment, ridiculously high taxes, rampant homelessness, I could go on...

    Report this post

  5. PetRealtor says...
    November 9, 2009 10:33:31 am

    Alive - what problems in Lidsville's last post do you not believe we are experiencing? And just who would you attribute these problems to?

    Report this post

  6. OB1 says...
    November 9, 2009 2:26:14 pm

    Obviously itâ??s the â??Politics as Usualâ?ť members of City Government to blame.

    Living in Petaluma we see the same ole faces in City Hall, positions change from year to year, but the same thought processes still prevail. These are many of the same folks that promise Rainer during an election year, but after the election; once again time stands still.

    Failed and stalled projects dot the landscape. (Itâ??s incredible!)

    Very poor management of City Government over the years has left citizens of Petaluma waiting at (awkwardly timed) stoplights in overcrowded intersections. When the light finally turns green you either get stuck in another red light (poor traffic engineering), or turn onto roads that are in such awful shape your suspension shakes to pieces.

    Petaluma needs new people to run for City office and bring a fresh management style that focuses on smart growth, and intelligent use of City funds. While Iâ??m not a big advocate (nor totally opposed) of the Regency deal, I will admit they got taken to the cleaners. The City got the new Junior High and stuffed Regencyâ??s face in the mud, at everybodyâ??s expense, whether you are for or against the project.

    Who wants a reputation like that?

    I see however a new â??Smoke shop /Mini Martâ?ť opened Downtown, just doors away from the Mystic. I guess these types of businesses are ok; it is the third shop of itâ??s kind now in the Downtown area.I guess instead of Target we got the â??Mini Martâ?ť part of the deal.

    Pathetic, vote them all out of office!

    Report this post

  7. king01 says...
    November 10, 2009 10:07:27 am

    Great neutral opinion.

    Report this post

  8. PTOWNKIDSTAXI says...
    November 10, 2009 12:59:33 pm

    I think we can trick the Majority Council to pass the much needed years of dragging feet overpass. Just rename it. "Duh" Overpass or "Smart" Overpass, "Torliatt" Overpass, this actually might get pushed thru with her name attatched to it.. It is obvious that the "Rainier" name is not getting it done..

    Report this post

  9. Tahoe says...
    November 10, 2009 2:53:47 pm

    LOL!!! "Torliatt Overpass"!

    Report this post

  10. alive says...
    November 10, 2009 4:09:11 pm

    The article attributes delays to three groups, none of which are the city or county government. One is a private contractor, one is the state and one is CalTrans. Perhaps there is some delay coming from the city and county, but the city is doing way more waiting than delaying on this one.

    Report this post

Next Article in Community-News