Michael and Vicky Farrow are looking forward to the next phase of the county's environmental restoration of Dry Creek, which will create a tranquil fish spawning habitat adjacent to their Amista Vineyards property, in Healdsburg.(Christopher Chung/ The Press Democrat)

Dry Creek restoration begins in summer

Sonoma County has approved a $4 million contract for the second phase of what could become a sweeping, $50 million environmental restoration project along Dry Creek west of Healdsburg.

The construction, scheduled for this summer, will complete the first of six miles of planned work along the creek, which serves as the artery for drinking water stored in Lake Sonoma to the north. Using the creek as an aqueduct to meet the needs of 600,000 residential and business customers in Sonoma and Marin counties has damaged the spawning grounds for delicate populations of steelhead trout and coho salmon, federal officials have concluded.

"The creek right now is a vibrant ecosystem," said David Manning, environmental resources coordinator for the Sonoma County Water Agency, "but it needs to be changed, in some places subtly and in some places dramatically" to accommodate the needs of the fish that once spawned there in great numbers.

The Sonoma County Board of Supervisors, which also heads the separate Water Agency, approved the contract unanimously last week.

Federal officials have ordered the agency, and the U.S. Army Corps of Engineers, which operates Warm Springs Dam at Lake Sonoma, to restore fish habitat by 2020. Because many details of the project remain uncertain, the Water Agency says, it is hard to tell how much the full project might cost or how the burden might be distributed among ratepayers and the state and federal governments. Estimates of the total cost run as high as $50 million.

That price, however, is cheaper than the alternative, Manning said, which would be to build a new underground pipeline to divert the drinking water flow out of the stream, allowing the creek to return to a more leisurely natural flow rate that is better suited to fish spawning. Such a pipeline could cost up to $150 million.

"That is a place we really do not want to go," Supervisors Chairman David Rabbitt said.

Dry Creek empties into the Russian River just south of Healdsburg and just a few miles upstream of the Water Agency's massive intakes near Wohler, where the water is piped to cities and special districts.

The agency's plan is to complete up to three miles of the restoration by 2018, at a cost of up to $20 million, then see if the fish populations are rebounding. If the first half of the project appears to be succeeding, another three miles would be restored; if not, county officials would have to dust off existing pipeline plans, he said.

Unlike the situation downstream of many reservoirs, where the dams may artificially reduce flows in the river, the problem in Dry Creek is too much water, as the agency draws from the lake in high volumes. In its natural state, Manning said, Dry Creek would see up to 10 cubic feet per second of water flowing during the summer, but since the dam was built in 1983, the flow has been around 10 times that.

While that means plenty of water for vegetation, insects, animals and people, it spells trouble for threatened fish, particularly the coho salmon, which are relatively poor swimmers and need quiet places to rest.

The restoration work, therefore, requires building side channels and ponds, and placing logs and boulders in the main channel to simulate the way the creek bed would have looked before agriculture, gravel mining and the water system operations took their toll. The hope is to allow the agency to continue to draw water from the reservoir at a higher-than-natural flow while still giving fish places to rest and hide from the current.

Most of the land along the creek is in private hands. Fortunately, Manning said, the wide and deep flood plain of the creek makes it easy to do the required work without affecting vineyards or homes. The agency has secured voluntary cooperation from all nine landowners along the first phases of the work, a fact that drew praise from the supervisors before the vote on the contract.

The first phase of the work, a half-million-dollar project last summer, saw some small side channels carved out along the edge of the Quivira Vineyards and Winery.

"If you were just a casual visitor walking around and didn't know what you were looking for, you might not see a big difference," said winery marketing director Andrew Fegelman.

Nearby landowner Peter Van Alyea said his vineyard operation will be disrupted somewhat by the new work this summer, as contractors dig a pond on a flat, gravelly spot between his vineyard and the creek, "but we'll work around it because it's the right thing to do."

When the work is done, he said, the pond should improve the appearance of the creek, in addition to helping the fish.

"It's not commercially viable: I can't put a vineyard there, I can't build a house there," he said. "This is an ideal use of the property."

The restoration will also be good for nearby Amista Vineyards winery, where fast-running water has eroded banks and toppled trees, owner Vicky Farrow said. The project will turn the existing barren dry wash into a slow moving side channel with reinforced banks.

"I think it will so beautify Dry Creek," she said. "In Dry Creek, the water comes rushing down when it rains and it causes a lot of damage."

UPDATED: Please read and follow our commenting policy:
  • This is a family newspaper, please use a kind and respectful tone.
  • No profanity, hate speech or personal attacks. No off-topic remarks.
  • No disinformation about current events.
  • We will remove any comments — or commenters — that do not follow this commenting policy.